118 UltraWAVE Micro BTS Installation and Commissioning Guide, Version B
Chapter 5 - On-Line Commissioning
5.2.4 External Alarm Tests
1 Test external alarms using the following procedures:
A Open the door of the Micro BTS.
B After a delay, the OMC operator must observe an alarm event.
C Close the door.
D After a delay, the alarm state displayed at the OMC changes from open to
closed.
2 For each external alarm that you connected in Section 2.8, verify that it is
propagated to the OMC.
A Close the alarm relay (i.e. trigger the first customer-defined alarm).
B After a delay, the OMC operator must observe an alarm event.
C Close the alarm relay by opening the alarm contact.
D After a delay, the alarm state displayed at the OMC changes from open to
closed.