114 UltraWAVE Micro BTS Installation and Commissioning Guide, Version B
Chapter 5 - On-Line Commissioning
5.2 On-Line Commissioning
The network commissioning procedures must be performed at the OMC and at the
Micro BTS. This requires two persons working from two different documentation
sets:
A field technician who remains on-site. They must have a filled out copy of
Checklist 2 - Installation Checklist and a copy of this manual.
An OMC operator who remains at the OMC. They must have a copy of the
UltraVIEW OMC Configuration Guide
.
The flow chart shown in Figure 5-1 provides a high-level view of the procedures.
The procedures in the following sections provide detailed, numbered steps.
Checklist 3 - Commissioning Checklist summarizes the steps for
on-line commissioning.
Before starting any of the following procedures, the field
technician needs to ensure that anti-static precautions are
taken. Refer to Section 1.2.