92 UltraWAVE Micro BTS Installation and Commissioning Guide, Version B
Chapter 3 - Off-Line Commissioning
3.5 Post Off-Line Commissioning
The following post off-line commissioning procedures are necessary to ensure that
the Micro BTS is ready for on-line commissioning. In the case of off-line
commissioning at a staging area, these procedures ensure that the Micro BTS is
ready for installation. In the case of off-line commissioning after on-site
installation, these procedures ensure that the Micro BTS is ready for on-line
commissioning.
3.5.1 Post Off-Line Commissioning Procedures at
the Staging Area
1 Repack the Micro BTS in its original shipping containers and make sure that it
is shipped to the site where it will be installed.
2 Once the Micro BTS is installed at its final site as described in Chapter 2 -
Installation, continue with the next section.
3.5.2 Post Off-Line Commissioning Procedures
On-Site
1 Reconnect the E1 or T1 cables to the digital distribution frame.
2 Power on the Micro BTS if it is not already on. Verify that all PWR and ON LINE
LEDs are green.
3 Inform the OMC operator that the Micro BTS is ready for network
configuration.
4 After the OMC operator has configured the Micro BTS, continue with on-line
commissioning tests in the next chapter.