Technical data

Installation
10 – EN ACT 600 – 5000
4.4 Installation layout
1
Air compressor
2
Aftercooler
3
Condensate separator
4
Pre-Filter (min. 5 micron)
5
By-pass group
6
Dryer
7
Compressed air tank
8
Final filter
9
Condensate drain
In case of heavily polluted inlet air (ISO 8573.1 class 3.-.3 or worse quality), we recommend
the additional installation of a pre-filter (5 micron minimum) to prevent a clogging of the
heat exchanger.
Type A installation is suggested when the compressor operates at reduced intermittence and the total
consumption equals the compressor flow rate.
Type B installation is suggested when the air consumption can consistently change with peak values highly
exceeding the flow rate of the compressors. The capacity of the tank must be sized in order to compensate
eventual instantaneous demanding conditions (peak air consumption).