Installation Instructions

Table Of Contents
MTU Instruction
for Invensys Icon MTU/Electric Meter Assembly
Purpose & Scope
This instruction provides a procedure for installing FORM 2s and FORM 12S Invensys
Icon MTU/Electric Meter Assemblies.
Supplies and Tools Required
Physical Installation of the ICON Form 2S
and Form 12S MTU/Electric Meter
Assemblies into compatible meter
sockets can be accomplished without the
use of tools.
Testing of the meter socket, however,
may require specialized equipment.
Check with the local electric utility for
required testing procedures.
WARNING!
Be sure to follow all local
safety procedures and do not
touch the exposed electrical
terminals in the meter socket.
These terminals carry the full
incoming service voltage.
Touching these terminals may
result in death or serious
injury.
Installation Procedure
Step 1 Complete all test procedures
required by the local electric utility and
verify that the meter socket has been
correctly installed and wired.
471-2007 - 2/28/2006
Page 41