Deployment Procedure
Deployment Procedure
The following procedure lists the steps required to deploy mulitport meters.
1. Install the electric meter epuipped with a TWACS module and an EMTR-3.
2. Install the ORION intelligent end device (IED).
3. Use the Listen List from the HHTR-3 to determine which ORION IEDs are
being heard by the selected EMTR-3.
4. Since the installer knows the ORION IED serial number, install the ORION
IED using the Listen List. If you hear nothing or obtain Error Code #33 (see
Error code descriptions and solutions on page 62) repeat this step.
5. If the ORION IED serial number is not in the Listen List, then program the
IED serial number into the ORION Connect ™ software in the Radix
handheld device. Listen for that particular serial number from a distance of
4-5 feet from the TWACS-equipped electric meter.
6. If you still cannot detect it, walk closer to the ORION IED to check if the
device is communicating.
7. If the ORION IED is heard within 4-5 feet of the EMTR-3 by the Radix
handheld device, but is not in the Listen List, check for another EMTR-3
within a clear line of sight and repeat the process.
N
OTES
This procedure is a recommendation, but it is not a requirement. Exact
installation procedures will be determined by the utility company and the
installers.
Multiple IEDs such as water, gas, or propane, do not need to be installed in any
particular order.
ORION water meters begin broadcasting when they detect a certain flow rate,
but ORION gas meters require installers to manually turn on the radio.