Installation Manual
Electrical installation
34
7.3 Connect the AC input cable
Preliminary requirements
•
Torque screwdriver
•
AC input cable (1 phase)
Procedure
4.
Connect the below wires:
1.
Earthing (grounding) wire
(A)
2.
L2 AC input wire (B)
3.
L1 AC input wire (C)
5.
Tighten the screws(D) to the
correct
torque. For the specification,
refer to section 10.14.
6.
Install the protect cover(F).
7.4 Communication connections
7.4.1
Insert the Ethernet cable
Preliminary requirements
1. The cabinet cover is removed.
2. The maintenance cover is removed.
Procedure
1.
Remove the grommet (A) from the
EVSE.
2.
Install the conduit.
3.
Put the Ethernet cable (B) through the
cable inlet hole.