Installation Manual
Installation
27
4
Installation
4.1
General installation procedure
Preliminary requirements
1.
All required permits to
agree with the local rules
are granted.
2.
The AC input cable is
available.
•
There is no voltage on the
AC input cable during the
complete installation
procedure.
•
Tools for installation. Refer
to section 11.7.
Procedure
1. Unpack the EVSE. Refer to section 4.2.
2. Prepare the site. Refer to chapter 5.
3. Do the mechanical installation. Refer to section 6.1.
4. Do the electrical installation. Refer to section 7.1.
5. Install the cabinet cover.
6. Do the commissioning procedure. Refer to section 8.1.
4.2
Unpack the EVSE
1. Open the box.
2. Remove the EVSE from the box.
3. Remove all packaging material from the EVSE.
4. Discard the packaging material. Refer to section 3.8.
5. Make sure that all parts are delivered according to the order. Refer to the
order and section 10.6.
6. Do an inspection of the EVSE and the parts for installation for damage.
7. If you find damage or the parts are not according to the order, contact
the local representative of the manufacturer (ABB EV Infrastructure).
Refer to section 1.12.